For a brand adding wooden parts or a wooden model to an existing metal range: what the project actually requires, in what order, and where the schedule usually slips.
A metal platform with a wooden variant is not a cosmetic change. The deck thickness changes the frame interface, the housing changes the venting, and the finish changes the packing. Suppliers who quote a wooden range from a photo produce a first sample that fits nothing; the sequence below is the one that avoids that.
Step 1: define the platform, not the picture
Which existing model is this a variant of? The answer fixes the frame mounting points, the motor envelope, the deck span and the handrail interface. Everything downstream — deck thickness, housing vent area, rail section — is derived from those four. If the wooden model is a new platform rather than a variant, say so at the start: the drawing workload is roughly double.
Step 2: choose species by function, then by look
Decks and rails carry load, so hardness and stability lead. Covers carry appearance and heat, so finish and venting lead. Handrails on senior machines are safety components, so section and fixing lead. The same species across all four is the cheapest way to guarantee a colour match, which is why most programs settle on Oak or Ash for the structural parts and use Walnut only where the colour is the selling point. Detail on the trade-offs is on the species page.
Step 3: drawing control
One drawing revision per part, referenced in the purchase order. Every change after the prototype gets a new revision number and a written confirmation. This sounds bureaucratic for a small program and is exactly what prevents a scrapped batch — the most common failure in wooden part programs is a verbal change to a hole position.
Step 4: prototype, then batch
The prototype proves three things at once: fit to the frame, finish match across parts, and thermal behaviour of the housing on a motorized unit. Only after that does batch production make sense. Prototype lead time: quoted per order.
Step 5: documentation and packing
Import documentation is part of the program, not an afterthought: species data for the Lacey Act declaration, ISPM 15 marking for wooden packaging, and the FSC position if the brand’s retail customer requires it. Packing is specified before production, because how a deck is supported in transit decides how many arrive flat. See compliance and documentation.
Where the schedule usually slips
- Venting decided late. A housing designed without the motor’s airflow path gets re-cut.
- Finish decided by sample, not by line. A sample panel finished by hand does not match a production finishing line; agree the finish system, not a swatch.
- Species changed after the prototype. Different species, different machining behaviour — the batch is re-cut.
- MOQ assumed. MOQ is quoted per order, and it differs between a part cut from stock and a part that needs a new machining setup.
← Applications | Motorized wooden treadmills | Start an OEM program →
OEM program questions
What does an OEM program actually include?
Five stages: drawing agreement, first-article sample, your approval, production batch, and the documentation package. The stage buyers skip is first-article approval, and it is the one that decides whether the batch fits — a sample approved verbally, without a signed drawing, is not an approval.
What is the first thing you need from us?
A drawing or a sample, the machine model it fits, the load case, the quantity band and the destination country. With those five, a quotation is a specification; without them it is a price list that will change after the first meeting.
How do you protect a customer’s design?
A confidentiality agreement is signed before drawings are exchanged if you ask for one, and your part geometry is not reused for another buyer. That is a commercial commitment we can put in writing at quotation stage rather than a policy statement on a website.
Specifications are indicative. Final dimensions and tolerances are confirmed at quotation.